ALAEN 314.7
22 January 1951
SUBJECT: Post Diary
TO: Commanding Officer
Camp Atterbury, Indiana
ATTN: Post Historian
1. On activation of Camp Atterbury, the duties and
responsibilities of the Post Engineer Organization pyramided from a
small maintenance group of thirty-one (31) people, plus fourteen (14)
firefighters, to an organization of close to one thousand (1,000)
civilian employees in a period of about three (3) weeks. During
this period of reorganization it was necessary to carry out high
priority activation projects, prepare plans and specifications for
several projects including the hospital, paving of roads, construction
of coal pads, replacement of smoke stacks on one hundred and eighty
(180) buildings, and about twenty (20) additional and equally important
projects. It was also necessary to to energize the permanent
civilian employees to high gear operation under extreme pressure.
Normal maintenance, of course, had to continue without interruption.
2. The type of personnel recruited by Civilian Personnel consisted
mostly of farmers and unemployed civilians in the immediate vicinity of
camp. Men who had at one time painted the kitchen at home, applied
as qualified painters, men who had fixed the farm pump applied as
qualified plumbers. Other building craft applicants ere equally
unqualified. Obviously this condition presented a state of
confusion in the entire organization with plenty of headaches and grey
hair to the Post Engineer who had only one officer (Captain Bentley) as
his assistant the first two (2) weeks, and he was involved full-time
ordering and expediting delivery of material and supplies. It took
considerable screening of personnel to find suitable supervisors and
group foremen qualified to direct operations on various activities.
3. About the middle of August 1950, two (2) officers arrived as
assistant to the Post Engineer, Lt. Colonel Ribbs (then Major), and
Major Bittner (then Captain). Colonel Ribbs was assigned as
Executive and Major Bittner as Chief of Operation Division. Well
qualified engineer non-commissioned officers were also assigned to this
organization as they arrived for duty at this camp. About the
first of September 1950, the administration and supervisory staff was
very well organized to carry on the assignment. During this
reorganization period, the administrative and clerical staff was
proportionately increased and trained in their respective duties.
4. Because of the tremendous amount of work to be done and the
short period of time in which to accomplish the first phase of our
mission, it meant working around the clock seven (7) days a week for the
first two (2) months. In the meantime, carloads after carloads of
lumber, railroad ties, coal, and equipment was rolling into camp, which
had to be unloaded and stored.
5. In addition to the purchase and hire activities of the Post
Engineer, the following contracts were awarded during August and
September.
Phase I at the Hospital
|
261,591
|
396 coal bins - Part 1
|
72,308
|
Replace 216 Garage Doors
|
52,098
|
Repaving and top dressing of camp roads
|
184,045
|
Replacing loading ramps
|
14,250
|
Reroofing several buildings
|
35,495
|
Construction of guard towers
|
5,224
|
Construction of vault in Building 103
|
2,100
|
19 Tank Crossings
|
13,940
|
Construction of 3 warehouses
|
128,362
|
Construction of 894 mess tables
|
26,280
|
Repair 9 well houses
|
1,495
|
Painting 39 mess halls
|
7,572
|
Replacing of smoke stacks
|
58,896
|
Construction of Range House
|
8,165
|
Replacing of perimeter gates and stockade
fence
|
12,811
|
Conversion of 4 SP-14 motor repair shops
|
42,557
|
Repair of bridge #16
|
23,572
|
Replace 25 vehicle grease racks
|
133,403
|
Some of the above contracts progresses very rapidly and according to
schedule, but a number of them were delayed due to shortage of critical
materials, principally steel items, and unfavorable weather conditions.
6. By the first of October 1950, everything was going along very
smoothly except that we were not accomplishing the amount of work with
our purchase and hire organization that was originally anticipated due
primarily to the poor grade of craftsmen we were able to employ at
established wage rates. It therefore became necessary to group
projects that could be done by contract and still protect the interests
of the Government. Plans ans specifications were prepared, bids
taken, and contracts awarded for the following projects:
Install sprinkler system in 7 warehouses and
shops
|
33,571
|
Construct ford crossing
|
6,823
|
Replace 4 igloos
|
24,860
|
Repair ration breakdown Bldg #7109
|
2,980
|
Construct 275 additional coal pads
|
44,716
|
Construction of 5 fire walls in Post Engineer
whses
|
12,787
|
Painting 15 P.X.'s and 2 Service Clubs
|
17.700
|
Painting 11 Chapels
|
11,899
|
Painting Post Library
|
2,770
|
Painting 12 Officers and NCO Messes
|
4,500
|
Painting 211 day rooms
|
59,125
|
Painting 14 dispensaries
|
5,367
|
Repair of 29 warehouses
|
67,349
|
Reconvert motor repair shop Bldg #7101
|
19,981
|
The last part of September 1950, it was evident that the hospital bed
capacity had to be increased. Immediate action was taken to
negotiate a contract for Phase II of hospital activation program.
On 7 October 1950, a contract in the amount of $462,438.oo was awarded
to cover Phase II.
7. In addition to the activation of the camp proper, the Post
Engineer was also charged with the construction and rehabilitation of
all training aids. Most of the training aids used during World War
II were either obsolete or had deteriorated to a point where they were
not economically reparable. All repairs on training aids that
could be used were accomplished by Purchase and Hire, however, because
of the urgent need for raining aids, contracts were awarded for the
following:
Construction of 2 gas chambers
|
12,995
|
Construction of 360 bayonet dummies
|
9,449
|
Construction of 3 confidence courses (labor
only)
|
7,500
|
Construction of combat village
|
15,826
|
Construction of 2 transition, 1 field target,
and 2 BAR ranges
|
57,232
|
Construction of 28 range latrines
|
17,829
|
During this period the following training aids were being constructed by
Post Engineer personnel:
2
|
mortar ranges
|
5
|
bayonet training areas
|
5
|
practice grenade courts
|
1
|
live grenade court
|
3
|
rifle grenade courses
|
1
|
rocket launcher range
|
1
|
recoilless rifle range
|
2
|
tank combat firing ranges
|
4
|
PRI circles
|
4
|
MG squares
|
1
|
mines and booby trap area
|
1
|
landscape target range
|
7. During the month of October 1950, we were informed that the
Post Engineer would go on an operational basis effective 15 November
1950.
Theoretically that meant that we would reduce our personnel ceiling to
operational strength or 482 spaces and would confine our activities to
maintenance and operation of post facilities. While we reduced the
organization to our authorized ceiling, thee was no reduction in
workload. This meant that we had to accomplish the same amount of
work with about 200 less spaces. There was a shortage of
transportation throughout the activation period causing considerable
delay in getting personnel and materials to work sites. This
bottleneck was partially eliminated when authority was granted to
contract for hauling of coal. This contract, based on delivery of 84,000
tons of coal will amount to approximately $31,500.00.
8. The months of November and December 1950 was more or less the
same as the preceding months, lots of work to be done and little time to
do it in. Our mission was complicated by cold weather causing an
excessive number of freeze ups due to improper or negligent firing
practices on the part of the troop units. During this period the
following contracts were awarded:
Painting 44 mess halls
|
12,900
|
Motor Pool fence
|
5,530
|
Salvage yard fence
|
5,200
|
Restoration of building #4106
|
3,997
|
Sprinklers in Building #7101
|
2,108
|
Construction of 740 additional mess tables
|
20,600
|
Ordnance shop fence
|
7,400
|
Replace 3 igloos
|
13,258
|
Linoleum and mastipave floor covering in Bldgs.
1312, 1369, 702, 507, 113, 1203, 107, 208, 210, 211, 212, 803,
and 14 dispensaries
|
20,370
|
Construction of 1 new theater
|
121,974
|
Rehabilitate electric system in Bldg. #7101
|
4,545
|
Repairs to laundry smoke stack
|
1,550
|
9. During the month of December, plans and specifications were
prepared for the following projects which are now in the hands of the
contractors:
Hospital Phase III
|
Additional 28 latrines
|
Chlorinators for pumping station
|
Carbine transition range
|
Rehabilitation Bldg #393
|
Rehabilitation Bldg #406
|
Construction of hitch-hiking sheds
|
Construction of hangar at air port
|
Construction of sidewalks in camp area
|
Extension to mess hall Bldg #1118
|
Note: This very briefly covers the major activities of Post
Engineer Organization up to 31 December 1950. It does by no means
cover minor activities, such as opening up plugged "Johns", repairing
leaky faucets, replacing burned out grates, collecting rubbish and
ashes, filling requisitions from units for lumber, paint, nails, stone,
signs, and a thousand other needs. Nor does it include fabrication
of non-standard items of furniture, shelves, partitions, doors, and
general repair and maintenance.
H. G. PETERSEN
Colonel, CE
Post Engineer
|